Demand Factor Estimate (NEC 220 Context)

Use user-defined load blocks and demand-factor percentages to create a transparent U.S. English preliminary estimate. NEC 220 is retained as legacy and topical search context; current NEC load-calculation numbering, including Article 120/220 context, must be verified against the adopted edition. This calculator does not reproduce NEC tables, dwelling-unit rules, or any adopted code calculation.

  • Updated August 22, 2026
Inputs
Result

Formulas

  • Applied first-block VA = first-block VA x first-block factor percent / 100
  • Applied remaining-block VA = remaining-block VA x remaining-block factor percent / 100
  • Estimated demand VA = fixed allowance VA + applied first-block VA + applied remaining-block VA
  • Total defined block VA = first-block VA + remaining-block VA
  • Unmodeled connected load VA = connected load VA - first-block VA - remaining-block VA
  • Diversity allowance VA = connected load VA - estimated demand VA
  • Effective demand factor percent = estimated demand VA / connected load VA x 100

A connected load figure by itself overstates the load a service or feeder will actually carry. Not every VA of connected equipment operates simultaneously at full output, so raw nameplate totals produce oversized conductor and overcurrent device selections if used directly. The Demand Factor Estimate calculator takes a connected load and applies user-defined block factors to produce an estimated demand VA figure — the number that feeds into preliminary conductor ampacity selection, feeder sizing discussions, and load-side equipment review before a full code-based load calculation is performed.

In the reference case, a connected load of 50,000 VA is split into a first-block load of 3,000 VA at a first-block factor of 100%, and a second user-defined block of 47,000 VA at a remaining-block factor of 50%. The result is an estimated demand from entered blocks of 26,500 VA — roughly half the connected load — which is the figure a designer would carry forward into conductor sizing rather than the full 50,000 VA nameplate total.

Inputs and What They Represent

The calculator accepts five entry fields:

  • Connected load (VA) — the total nameplate or calculated load before any demand factor is applied.
  • First-block load (VA) — the portion of connected load assigned to the first demand tier, typically the tier most likely to run near full capacity.
  • First-block factor (%) — the percentage of the first-block load counted toward demand.
  • Second user-defined block (VA) — the remaining portion of load assigned to a second tier, usually the larger, more diversified portion of the load.
  • Remaining-block factor (%) — the percentage of the second block counted toward demand.
  • Fixed allowance (VA) — an optional flat VA addition applied directly to the demand total, independent of either block.

These fields do not correspond to any single fixed NEC table. They are generic block-and-factor inputs that let a user model any two-tier demand structure — whether drawn from a dwelling-unit table, a commercial lighting demand schedule, or an internal engineering estimate — without the calculator hardcoding a specific code table.

Formula Behavior

The calculator runs six linked calculations:

Applied first-block VA = first-block VA × first-block factor % / 100 Applied remaining-block VA = remaining-block VA × remaining-block factor % / 100 Estimated demand VA = fixed allowance VA + applied first-block VA + applied remaining-block VA Total defined block VA = first-block VA + remaining-block VA Unmodeled connected load VA = connected load VA − first-block VA − remaining-block VA Diversity allowance VA = connected load VA − estimated demand VA

A seventh figure, effective demand factor %, is derived as estimated demand VA ÷ connected load VA × 100, giving a single percentage that summarizes how much diversity credit the block structure produced relative to the full connected load.

Calculation Example

Using the reference inputs — 50,000 VA connected load, first block 3,000 VA at 100%, remaining block 47,000 VA at 50%, fixed allowance 0 VA:

FieldValue
Applied first-block demand3,000 VA
Applied remaining-block demand23,500 VA
Total defined load blocks50,000 VA
Unmodeled connected load0 VA
Estimated demand from entered blocks26,500 VA
Diversity allowance from entered blocks23,500 VA
Effective demand factor53%

Because the two blocks (3,000 + 47,000 = 50,000 VA) equal the full connected load, unmodeled connected load is 0 VA. If a user enters block totals that fall short of the connected load figure, that field reports the gap — VA that has not been assigned a demand factor and is excluded from the estimated demand result. That gap must be resolved manually; the calculator will not distribute it automatically or apply a default factor to it.

Where the Output Is Used

The estimated demand VA result is the starting point for downstream feeder and service work: conductor ampacity selection, overcurrent protective device sizing, panel schedule load entries, and voltage-drop review at the estimated operating current rather than the full connected-load current. The diversity allowance VA figure — 23,500 VA in the example — quantifies how much load capacity is being deferred to diversity rather than continuous simultaneous operation, which is useful when documenting load calculations for an AHJ review or comparing design margin against actual measured demand from utility or monitoring data.

Code and Field Limitations

This calculator performs arithmetic on user-supplied blocks and factors. It does not reproduce any NEC dwelling-unit demand table, does not apply Article 220 load calculation methods automatically, and does not select factors on the reader’s behalf. NEC 220 is referenced here as legacy and topical context only; current load-calculation numbering — including any Article 120/220 renumbering — must be confirmed against the code edition adopted by the local AHJ before a demand factor derived from this tool is used in a submitted load calculation.

The first-block and remaining-block structure models a simple two-tier demand schedule. It does not handle multi-tier tables, motor load additions with separate demand rules, continuous-duty multipliers, or receptacle/lighting load categories that carry distinct demand treatment under an adopted code. Any of those conditions require a calculation method specific to the governing code section, performed separately from this estimate. Verify final conductor and overcurrent device selections against the adopted code edition and local amendments before construction.

FAQs

Does this calculator reproduce NEC 220 demand-factor tables?

No. NEC 220 is legacy and topical context, but this tool applies the block sizes and percentages that you enter. Current NEC Article 120/220 numbering, adopted-code text, AHJ direction, and project method must be verified separately. This calculator does not encode or reproduce NEC tables, load classifications, or adopted-code requirements.

What is the first block and remaining block?

They are user-defined portions of the connected load. Assign them only after deciding how your project should be screened; the labels do not identify a specific NEC table or mandatory code threshold.

What does the effective demand factor show?

It is the estimated demand divided by connected load, expressed as a percentage. It summarizes the assumptions entered here and is not a code-approved demand factor.

Can I use this for permit or service sizing?

No. It is a screening worksheet for user-entered assumptions. It does not produce an adopted-code demand calculation, feeder calculation, service-size decision, conductor selection, breaker selection, utility approval, or permit-ready result.

Where should the entered factors come from?

They must come from a separately verified project method, such as an adopted NEC edition review, AHJ direction, engineering calculation, utility requirement, or documented internal screening method. This calculator does not choose them.