Pull Box Sizing Calculator
Estimate preliminary pull-box dimension references from the largest raceway and same-wall raceway sum before verifying NEC 314.28 and the installed layout.
- Straight-pull length reference
- in
- Angle-pull length reference
- in
- Recommended minimum screening length
- in
- Largest raceway used
- in
- Same-wall raceway sum used
- in
- Selected pull type
- Straight-pull multiplier
- x
- Angle or U pull multiplier
- x
- Controlling screening reference
- in
Calculation details
- Controlling reason
- Calculation basis
- NEC 314.28 boundary
- Layout boundary
- Conductor-size boundary
- Splice/U-pull boundary
- Code-compliance boundary
Recent results
Formulas
- \(\text{Straight-pull reference} = 8D\)
- \(\text{Angle or U pull reference} = 6D + S_{\text{same-wall}}\)
- \(\text{Controlling reference} = \max(\text{straight reference}, \text{angle/U reference})\)
- straight-pull reference = 8 x largest raceway size
- angle or U pull reference = 6 x largest raceway size + same-wall raceway sum
- controlling screening reference = straight reference for straight pulls; max(straight reference, angle or U reference) for conservative angle or U screening
- code-compliance boundary = no final NEC, AHJ, manufacturer, conductor-bend-radius, splice, box-fill, enclosure, listing, installation, or inspection approval is made by this calculator
Related tools: Short-Circuit Current Calculator, Conduit Fill Calculator, and Conduit Cut Length Calculator.
What This Calculator Does
This tool is a screening-level worksheet for estimating the minimum interior dimension of a pull box, junction box, or conduit body under NEC 314.28 — Pull and Junction Boxes and Conduit Bodies. It applies the two governing formulas (straight pull and angle/U pull) to the raceway sizes you enter and returns the larger, controlling value as a starting reference. It does not select a final box, does not check box fill under 314.16, and does not account for splices, conductor bending space, gutter space, manufacturer listing limitations, or your local Authority Having Jurisdiction’s (AHJ) interpretation — all of which must be verified separately before specifying a box.
Code Basis and Edition
The 8× and 6× multipliers used here come from NEC Article 314.28(A)(1) and (A)(2). As of mid-2026, NEC 2023 remains the edition adopted by most U.S. jurisdictions, while a smaller number of states (e.g., Massachusetts, Texas) have moved to NEC 2026. The numeric multipliers (8× for straight pulls, 6× plus row sum for angle/U pulls and splices) are unchanged between the 2023 and 2026 editions. Confirm which edition your local AHJ has adopted before finalizing any box selection, since section numbering, exceptions, and enforcement practices can still vary by jurisdiction.
Straight-Pull Formula — NEC 314.28(A)(1)
For a straight pull, where conductors enter one wall of the box and exit through the opposite wall without changing direction, the box length in the direction of the pull must be at least 8 times the trade size of the largest raceway entering that wall:
\(\displaystyle L_{straight} = 8 \times D_{largest}\)
Worked example (matches calculator inputs): Largest raceway = 2 in.
\(L_{straight} = 8 \times 2\text{ in} = 16\text{ in}\) This is the value shown as “Straight-pull length reference: 16 in.”
Angle, U-Pull, and Splice Formula — NEC 314.28(A)(2)
For angle pulls, U pulls, or where splices are made, the distance from each raceway entry to the opposite wall of the box must be at least 6 times the trade size of the largest raceway in that row, increased by the sum of the trade sizes of all other raceways entering on the same wall and same row:
\(\displaystyle L_{\text{angle/U}} = 6 \times D_{\text{largest}} + \sum D_{\text{other}}\) + \sum D_{other\ raceways\ on\ same\ wall}\)
Each wall and row must be evaluated separately, and the single row producing the largest result governs.
Worked example (matches calculator inputs): Largest raceway = 2 in; sum of other same-wall raceway sizes = 3 in.
\(L_{\text{angle/U}} = 6 \times 2\text{ in} + 3\text{ in} = 15\text{ in}\)\) + 3\text{ in} = 12\text{ in} + 3\text{ in} = 15\text{ in}\) This is the value shown as “Angle-pull length reference: 15 in.”
Controlling Dimension
The calculator compares both results and returns the larger one as the recommended minimum screening length:
\(\displaystyle L_{controlling} = \max(L_{straight},\ L_{angle/U})\)
With the inputs above (16 in vs. 15 in), the straight-pull value of 16 in controls, matching the “Recommended minimum screening length: 16 in” and “Controlling screening reference: 16 in” outputs. If your layout includes both straight and angle/U pulls at different walls, calculate each wall independently and size the box to satisfy the largest requirement across all walls.
Additional Requirements Not Captured by This Screening Tool
NEC 314.28 and related sections impose several requirements this worksheet does not evaluate:
- Conductor-enclosing raceways: the distance between raceway entries enclosing the same conductor must be at least 6 times the trade size of the larger raceway.
- Box-fill limits under 314.16 for any splices, taps, or devices housed in the enclosure.
- Bending space and gutter space for conductors, per manufacturer instructions and 312.6 where applicable.
- Exception allowances for conductors entering the back of an enclosure opposite a removable cover, which use conductor-size-based minimums (e.g., 3 in for 1 AWG, 3½ in for 1/0–2/0 AWG, 4 in for 3/0–4/0 AWG) rather than the 6× rule.
- Manufacturer catalog dimensions, listing constraints, and any local amendments enforced by your AHJ.
FAQs
Does this tool determine my final box size?
No. It provides a minimum reference length based on the 8× and 6× multipliers only. Final box selection requires checking conductor count, splices, box fill, bend radius, and manufacturer availability.
Which raceway size do I use if I have multiple conduits on one wall?
Use the largest trade size on that wall as n𝐷n𝑙n𝑎n𝑟n𝑔n𝑒n𝑠n𝑡nD nlargestnn in the applicable formula, then add the trade sizes of the remaining raceways on the same wall for angle/U pulls.