Panel Load Schedule Worksheet

Print this worksheet to record panel circuits, connected loads, demand notes, calculated totals, and the review basis for panel or service sizing.

  • Updated August 27, 2026

A panel load schedule organizes the circuit-by-circuit information needed to review an electrical panel before making feeder, service, overcurrent protection, or conductor-sizing decisions. The key recorded result is the panel total, expressed in VA or A. That total becomes a project input for demand-load review and for the related Electrical Panel Load Calculator.

A panel schedule is not just a panel directory. A directory identifies where branch circuits go; a load schedule records what those circuits supply, the connected load assigned to each circuit, whether a load is continuous, and the method or source used to determine the final calculated load.

Use the worksheet to collect the project data first, then document the calculation results and design selections that follow.

Open Electrical Panel Load Calculator

Panel and Circuit Data

Start by identifying the panel and electrical system. Record the project name, panel name or designation, system voltage, and phase exactly as shown on the project documents or existing equipment.

For each circuit, enter:

Worksheet field What to record
Project name Project, address, unit, or job reference used in the project record
Panel name or designation Panel identifier, such as Panel A, LP-1, or an existing-panel designation
System voltage (V) The actual project voltage
Phase The project phase configuration
Circuit number Circuit identifier used in the panel directory or working schedule
Load description Clear description of the supplied equipment, receptacle load, lighting load, appliance, or dedicated branch circuit
Connected load (VA or W) Load value obtained from documents, equipment nameplates, measurements, or related calculator results
Continuous load flag (yes/no) Whether the project load review treats the circuit load as continuous

Use consistent circuit descriptions. If the panel directory says “Kitchen Counter Receptacles,” the worksheet should not use a vague substitute such as “Kitchen.” Consistent naming makes it easier to trace a calculated panel total back to the branch circuit, equipment schedule, or field condition that produced it.

Connected load may be entered in volt-amperes or watts, according to the available project information. Record the unit used and maintain that unit consistently while developing the schedule.

Connected Load and Demand Review

The connected-load entry is the starting point; it is not necessarily the final load used for feeder or service sizing. The worksheet separates connected load from calculated load so the project can document the demand factor or calculation method applied to the panel.

Record the following in the demand and sizing section:

Worksheet field What to record
Demand factor or method note The demand approach, calculation method, or project basis used for the load review
Calculated load (VA or A) Result after applying the selected load calculation method
Breaker or OCPD size (A) The selected overcurrent protective device size and the source or method supporting that selection

The related calculator may convert and total the entered electrical loads, but demand factors, continuous-load treatment, and final feeder or service decisions remain project-specific. Verify the adopted electrical code, local amendments, utility requirements, equipment instructions, and AHJ interpretation before finalizing a panel, feeder, service, or OCPD selection.

For a voltage-based conversion from apparent power to current, use the project system voltage and the applicable system configuration. The worksheet records the resulting value in VA or A, rather than imposing a single conversion method across all panel types.

Continuous Load Entries

The continuous load flag creates a clear review point for circuits that may require different treatment than noncontinuous loads. Enter “yes” or “no” based on the project load classification and the applicable design requirements.

Do not assume that all equipment on a dedicated branch circuit has the same loading treatment. A dedicated circuit can supply a continuous load, noncontinuous load, motor load, appliance load, or equipment with manufacturer-specific electrical requirements. The schedule should identify the load accurately enough for the project reviewer to determine the correct treatment.

Examples of useful load descriptions include:

  • Exterior lighting
  • EV charging equipment
  • Air-conditioning condenser
  • Electric range
  • Water heater
  • General lighting
  • Receptacle load
  • Pool equipment
  • Mechanical unit
  • Spare circuit

The final branch-circuit conductor ampacity, AWG or kcmil selection, terminal rating, insulation temperature rating, adjustment factor, correction factor, raceway fill, and voltage-drop review are separate design checks. The load schedule supplies the documented load data used for those checks.

Panel Total and Feeder Review

Add or record the calculated circuit loads to establish the panel total (VA or A). This is the number used to compare the panel’s calculated demand with the intended panel, feeder, service, and upstream distribution arrangement.

A completed panel total supports several practical workflows:

  • Reviewing whether the panel load aligns with the project’s feeder or service calculation.
  • Identifying large dedicated loads that may affect the feeder, service, or load-management approach.
  • Providing documented load values for conductor ampacity and OCPD review.
  • Checking whether a proposed panel change affects the upstream distribution equipment.
  • Preserving the basis for future remodel, tenant-improvement, or equipment-addition reviews.
  • Creating a clearer record when actual field conditions differ from original drawings.

A panel total by itself does not establish conductor size or breaker size. Final conductor selection may require ampacity review, ambient-temperature correction, adjustment for current-carrying conductors, terminal limitations, equipment listing instructions, voltage-drop considerations, and installation conditions. Final OCPD selection also depends on the applicable load rules and equipment requirements.

Completing the Worksheet

Use the worksheet fields in sequence:

1. Record the project name, panel designation, voltage, and phase.

  1. Enter each circuit number and load description using the same naming convention as the panel directory or project schedule.
  2. Record connected load in VA or W from project documents, nameplates, measurements, or calculation outputs.

4. Mark the continuous-load flag for each applicable circuit.

5. Document the demand factor or load-calculation method used.

6. Record the calculated load in VA or A.

7. Record the selected breaker or OCPD size and the basis for that selection.

8. Record the panel total, review notes, and date.

Keep the source or notes column specific. “Plans,” “nameplate,” “field measurement,” “load calculation,” or a project document reference provides a usable trail for later review. General notes such as “checked” do not show where a load value or OCPD decision came from.

Field Verification

Verify the worksheet against the current project condition before using it for a final panel, feeder, or service decision. Existing panels may have incomplete directories, relocated loads, added equipment, shared circuits, or field modifications not reflected on drawings.

Confirm that:

  • Circuit numbers match the actual panel directory or current working schedule.
  • Load descriptions identify the equipment or area served.
  • Connected-load values come from a documented project source.
  • Continuous-load entries reflect the project’s adopted requirements.
  • Demand-method notes identify the basis for the calculated result.
  • Panel totals and review notes are dated and retained with the project record.

The completed panel load schedule provides the organized circuit data needed for a documented load review; final electrical design and installation decisions must be checked against the adopted requirements and the AHJ.

Calculators for this topic

The tools this guide links to, for the same calculation.