Power Quality And Transformers

Transformer kVA, primary current, secondary current, impedance, inrush, K-factor, generator sizing, and UPS capacity.

Sub-topics in this category

Equipment Review

Equipment-data and nameplate review workflows.

Transformer Testing

Transformer test, impedance, and nameplate verification workflows.

Engineering Estimate

Formula-backed estimates that require professional verification before final use.

Capacity Margin

Capacity, margin, and preliminary headroom screens.

Line Current

Line-current and phase-model arithmetic workflows.

Power Factor

Power-factor and apparent-power conversion workflows.

Voltage Readings

Voltage measurements and voltage-ratio comparison workflows.

Energy Cost

Energy-use, rate, and operating-cost calculations.

Harmonics

Harmonic-current and power-quality screening workflows.

Power Electronics

Power-electronics and component behavior screens.

Backup Power

Generator and backup-power planning workflows.

Commercial Load

Commercial and industrial connected-load workflows.

Fault Current

Preliminary fault-current and short-circuit contribution screens.

Testing and Measurement

Measured test data, instrument readings, and field measurement calculations.

Field Verification

Measured field data reduction and verification workflows.

Load Accounting

Transparent connected-load and worksheet accounting workflows.

Grounding

Grounding and earth-electrode measurement workflows.

UPS

Uninterruptible power supply capacity and runtime workflows.

Voltage Drop

Voltage-drop and conductor-length calculation workflows.

What this topic covers

About this category

32 calculators are grouped under Power Quality And Transformers, and the work splits into Equipment Review, Transformer Testing, Engineering Estimate, Capacity Margin. Every page states the formula it applies, the inputs and units it expects, and the limits of the estimate, so a result can be checked against the adopted code edition and the equipment nameplate before it is used for a design decision.

Written for Electricians, Engineers, Estimators, Facility Teams, Inspectors, and Technicians.

Basis cited across this topic: ANSI C57 (8), IEC (4), IEEE (19), NFPA 70 (NEC) (5), UL (1). Each calculator lists its own source citation and review dates on its page.

Formulas used in this category

The arithmetic the 32 calculators in Power Quality And Transformers apply, in the order it is evaluated. These are calculation summaries, not code text — verify each against the source standard before design use. Full explanations for every topic are in the formula reference index.

Show formula sheet (32 calculators)
Buck-Boost Transformer Calculator
  • \(m_{\text{phase}}=1\text{ for single-phase},\quad m_{\text{phase}}=\sqrt{3}\text{ for balanced three-phase}\)
  • \(\Delta V = V_{\text{target}} - V_{\text{supply}}\)
  • \(S_{\text{load}} = \frac{I \times V_{\text{target}} \times m_{\text{phase}}}{1000}\)
  • \(S_{\text{winding}} = \frac{I \times |\Delta V| \times m_{\text{phase}}}{1000}\)
  • \(S_{\text{required}} = S_{\text{winding}} \times \frac{F_{\text{sizing}}}{100}\)
Capacitor Bank Size Calculator
  • \(P=\text{real power},\quad PF_{\text{current}}=\text{current power factor},\quad PF_{\text{target}}=\text{target power factor}\)
  • \(f=\text{frequency},\quad V=\text{system voltage},\quad k_{\text{connection}}=3\text{ for three-phase delta
  • otherwise }1\)
  • \(Q_{\text{current}} = P \times \tan\left(\cos^{-1}(PF_{\text{current}})\right)\)
  • \(Q_{\text{target}} = P \times \tan\left(\cos^{-1}(PF_{\text{target}})\right)\)
  • \(Q_C = Q_{\text{current}} - Q_{\text{target}}\)
Generator Size Calculator
  • \(\text{Margin multiplier} = 1 + \frac{\text{Planning margin (\%)}}{100}\)
  • \(\text{Running rating (W)} = \text{Running watts} \times \text{Margin multiplier}\)
  • \(\text{Surge rating (W)} = (\text{Running watts} + \text{Largest starting watts} + \text{Other simultaneous starting watts}) \times \text{Margin multiplier}\)
  • \(\text{Required kVA} = \frac{\text{Surge rating (W)}}{1000 \times \text{Power factor}}\)
Harmonic Distortion Calculator
  • \(I_{h,\mathrm{combined}} = \sqrt{I_2^2 + I_3^2 + I_5^2 + I_7^2}\)
  • \(\mathrm{THD}(\%) = \frac{I_{h,\mathrm{combined}}}{I_1} \times 100\)
  • \(\mathrm{Harmonic}_n(\%) = \frac{I_n}{I_1} \times 100\quad(n \in \{2,3,5,7\})\)
Power Factor Correction Calculator
  • \(\displaystyle Q_{\text{current}}=P\tan(\arccos(\mathrm{PF}_{\text{current}}))\)
  • \(\displaystyle Q_{\text{target}}=P\tan(\arccos(\mathrm{PF}_{\text{target}}))\)
  • \(\displaystyle Q_{\text{correction}}=Q_{\text{current}}-Q_{\text{target}}\)
  • \(\displaystyle \Delta I=\frac{(S_{\text{current}}-S_{\text{target}})\times1000}{k_{\phi} V}\)
Power Quality Crest Factor Calculator
  • \(\mathrm{Crest\ factor} = \frac{X_{\mathrm{peak}}}{X_{\mathrm{RMS}}}\)
  • \(X_{\mathrm{peak-to-peak}} = X_{\mathrm{positive\ peak}} + |X_{\mathrm{negative\ peak}}|\)
  • \(X = V\ \mathrm{or}\ I\ \mathrm{from\ the\ selected\ measurement\ type}\)
Transformer All-Day Efficiency Calculator
  • \(E_{\mathrm{output}} = \sum_i \mathrm{kVA}_{\mathrm{rated}} F_i PF_i h_i\)
  • \(E_{\mathrm{core\ loss}} = \sum_i \frac{P_{\mathrm{no-load}} h_i}{1000}\)
  • \(E_{\mathrm{load\ loss}} = \sum_i \frac{P_{\mathrm{full-load\ loss}} F_i^2 h_i}{1000}\)
  • \(E_{\mathrm{input}} = E_{\mathrm{output}} + E_{\mathrm{core\ loss}} + E_{\mathrm{load\ loss}}\)
  • \(\eta_{\mathrm{all-day}} = \frac{E_{\mathrm{output}}}{E_{\mathrm{input}}} \times 100\%\)
Transformer Bank Capacity Calculator
  • \(\text{Total nameplate capacity} = \text{Unit count} \times \text{Unit kVA}\)
  • \(\text{Utilization ratio} = \frac{\text{Utilization percent}}{100}\)
  • \(\text{Usable capacity} = \text{Total nameplate capacity} \times \text{Utilization ratio}\)
  • \(\text{Reserved capacity} = \text{Total nameplate capacity} - \text{Usable capacity}\)
Transformer Cooling Load Calculator
  • \(\text{Adjusted heat load} = \text{Transformer losses} \times \frac{\text{Diversity percent}}{100} \times \left(1 + \frac{\text{Safety factor percent}}{100}\right)\)
  • \(\text{BTU per hour} = \text{Adjusted heat load (W)} \times 3.412142\)
  • \(\text{Cooling tons} = \frac{\text{BTU per hour}}{12000}\)
  • \(\text{Daily heat energy (kWh)} = \frac{\text{Adjusted heat load (W)} \times \text{Operating hours}}{1000}\)
Transformer Current Calculator
  • \(\text{Transformer apparent power (VA)} = \text{Transformer size (kVA)} \times 1{,}000\)
  • \(\text{Single-phase current} = \frac{\text{VA}}{\text{Voltage}}\)
  • \(\text{Three-phase current} = \frac{\text{VA}}{\sqrt{3}\times\text{Line voltage}}\)
Transformer Delta-Wye Voltage Calculator
  • \(\text{Secondary line voltage} = \frac{\text{Primary line voltage}}{\text{Turns ratio}}\)
  • \(\text{Wye phase voltage} = \frac{\text{Secondary line voltage}}{\sqrt{3}}\)
  • \(\text{Delta phase voltage} = \text{Secondary line voltage}\)
Transformer Efficiency Calculator
  • \(\eta = \frac{P_{\mathrm{output}}}{P_{\mathrm{input}}} \times 100\%\)
  • \(P_{\mathrm{loss}} = P_{\mathrm{input}} - P_{\mathrm{output}}\)
Transformer Generator Coordination Calculator
  • \(\text{Estimated load (kVA)} = \text{Transformer kVA} \times \frac{\text{Expected load percent}}{100}\)
  • \(\text{Estimated load (kW)} = \text{Estimated load (kVA)} \times \text{Load power factor}\)
  • \(\text{kVA margin} = \text{Generator kVA rating} - \text{Estimated load (kVA)}\)
  • \(\text{kW margin} = \text{Generator kW rating} - \text{Estimated load (kW)}\)
  • \(\text{kVA utilization} = \frac{\text{Estimated load (kVA)}}{\text{Generator kVA rating}}\)
  • \(\text{kW utilization} = \frac{\text{Estimated load (kW)}}{\text{Generator kW rating}}\)
Transformer Grounding Resistor Calculator
  • \(\text{Resistor resistance} = \frac{\text{Line-to-neutral voltage}}{\text{Target ground-fault current}}\)
  • \(\text{Resistor power (kW)} = \frac{\text{Voltage} \times \text{Current}}{1000}\)
  • \(\text{Fault energy (kJ)} = \frac{\text{Voltage} \times \text{Current} \times \text{Duration}}{1000}\)
  • \(\text{Current-rating margin} = \text{Entered resistor current rating} - \text{Target current}\)
Transformer Harmonic Heating Calculator
  • \(\text{Harmonic RMS current} = \text{Fundamental current} \times \frac{\text{THD percent}}{100}\)
  • \(\text{Total RMS current} = \sqrt{\text{Fundamental current}^{2} + \text{Harmonic current}^{2}}\)
  • \(\text{RMS heating factor} = \left(\frac{\text{Total RMS current}}{\text{Fundamental current}}\right)^{2}\)
  • \(\text{THD ratio} = \frac{\text{THD percent}}{100}\)
  • \(\text{Weighted heating factor} = 1 + \left(\text{THD ratio}^{2} \times \text{Eddy weighting multiplier}\right)\)
  • \(\text{Adjusted stray loss} = \text{Base stray loss} \times \text{Weighted heating factor}\)
Transformer Impedance Calculator
  • \(\text{Base current} = \frac{\text{kVA}\times1{,}000}{\text{Phase multiplier}\times\text{Voltage}}\)
  • \(\text{Base impedance} = \frac{\text{Voltage}}{\text{Phase multiplier}\times\text{Base current}}\)
  • \(\text{Per-unit impedance} = \frac{\text{Impedance percent}}{100}\)
  • \(\text{Impedance (ohm)} = \text{Base impedance}\times\text{Per-unit impedance}\)
  • \(\text{Transformer-limited current} = \frac{\text{Base current}}{\text{Per-unit impedance}}\)
Transformer Inrush Current Calculator
  • \(\text{Transformer apparent power (VA)} = \text{Transformer size (kVA)} \times 1{,}000\)
  • \(\text{Single-phase rated current} = \frac{\text{VA}}{\text{Voltage}}\)
  • \(\text{Three-phase rated current} = \frac{\text{VA}}{\sqrt{3}\times\text{Line voltage}}\)
  • \(\text{Estimated inrush current} = \text{Rated current}\times\text{Inrush multiplier}\)
Transformer Inrush Duration Calculator
  • \(\text{Initial multiplier} = \frac{\text{Initial inrush current}}{\text{Steady-state current}}\)
  • \(\text{Target current} = \text{Steady-state current} \times \text{Target multiplier}\)
  • \(\text{Duration (cycles)} = \text{Decay time constant} \times \ln\!\left(\frac{\text{Initial multiplier}}{\text{Target multiplier}}\right)\)
  • \(\text{Duration (seconds)} = \frac{\text{Duration (cycles)}}{\text{Frequency}}\)
Transformer K-Factor Calculator
  • \(K = \sum_h \left(\frac{I_h}{I_{\mathrm{ref}}}\right)^2 h^2\)
  • \(I_h = \mathrm{true\ RMS\ current\ at\ harmonic\ order}\ h\)
  • \(I_{\mathrm{ref}} = \mathrm{entered\ fundamental\ or\ rated\ current\ basis}\)
Transformer kVA Calculator
  • \(S_{1\phi} = \frac{V \times I}{1000}\,\mathrm{kVA}\)
  • \(S_{3\phi} = \frac{\sqrt{3} \times V_{LL} \times I_L}{1000}\,\mathrm{kVA}\)
  • \(P = S \times \mathrm{PF}\,\mathrm{kW}\)
Transformer Losses Calculator
  • \(P_{\mathrm{loss}} = P_{\mathrm{core}} + P_{\mathrm{load}}\)
  • \(P_{\mathrm{input}} = P_{\mathrm{output}} + P_{\mathrm{loss}}\)
  • \(\eta = \frac{P_{\mathrm{output}}}{P_{\mathrm{input}}} \times 100\%\)
Transformer Percent Impedance Test Calculator
  • \(a = \frac{V_{\mathrm{primary,rated}}[\mathrm{V}]}{V_{\mathrm{test\ winding,rated}}[\mathrm{V}]}\)
  • \(\Delta I_{\%} = \frac{\left|I_{\mathrm{test}}[\mathrm{A}]-I_{\mathrm{rated}}[\mathrm{A}]\right|}{I_{\mathrm{rated}}[\mathrm{A}]}\times100\)
  • \(I_{\mathrm{ratio}} = \frac{I_{\mathrm{test}}[\mathrm{A}]}{I_{\mathrm{rated}}[\mathrm{A}]}\)
  • \(Z_{\%} = \frac{V_{\mathrm{test}}[\mathrm{V}]}{V_{\mathrm{test\ winding,rated}}[\mathrm{V}]}\times100\)
Transformer Primary Current Calculator
  • \(S_{\mathrm{VA}}[\mathrm{VA}] = S_{\mathrm{kVA}}[\mathrm{kVA}]\times1000\)
  • \(k_{\mathrm{phase}}=1\text{ for single-phase
  • }k_{\mathrm{phase}}=\sqrt{3}\text{ for balanced three-phase}\)
  • \(I_{\mathrm{primary}}[\mathrm{A}] = \frac{S_{\mathrm{VA}}[\mathrm{VA}]}{k_{\mathrm{phase}}V_{\mathrm{primary}}[\mathrm{V}]}\)
Transformer Regulation Calculator
  • \(\Delta V = V_{\mathrm{no-load}} - V_{\mathrm{full-load}}\)
  • \(\mathrm{Voltage\ regulation} = \frac{\Delta V}{V_{\mathrm{full-load}}} \times 100\%\)
Transformer Secondary Current Calculator
  • \(S_{\mathrm{VA}}[\mathrm{VA}] = S_{\mathrm{kVA}}[\mathrm{kVA}]\times1000\)
  • \(k_{\mathrm{phase}}=1\text{ for single-phase
  • }k_{\mathrm{phase}}=\sqrt{3}\text{ for balanced three-phase}\)
  • \(I_{\mathrm{secondary}}[\mathrm{A}] = \frac{S_{\mathrm{VA}}[\mathrm{VA}]}{k_{\mathrm{phase}}V_{\mathrm{secondary}}[\mathrm{V}]}\)
Transformer Service Factor Calculator
  • \(S_{\mathrm{available}}[\mathrm{kVA}] = S_{\mathrm{nameplate}}[\mathrm{kVA}]\times f_{\mathrm{service}}[\mathrm{x}]\)
  • \(U_{\%} = \frac{S_{\mathrm{load}}[\mathrm{kVA}]}{S_{\mathrm{available}}[\mathrm{kVA}]}\times100\)
  • \(M[\mathrm{kVA}] = S_{\mathrm{available}}[\mathrm{kVA}] - S_{\mathrm{load}}[\mathrm{kVA}]\)
Transformer Short Circuit Contribution Calculator
  • \(k_{\mathrm{phase}}=1\text{ for single-phase
  • }k_{\mathrm{phase}}=\sqrt{3}\text{ for balanced three-phase}\)
  • \(I_{\mathrm{rated}}[\mathrm{A}] = \frac{S_{\mathrm{transformer}}[\mathrm{kVA}]\times1000}{k_{\mathrm{phase}}V_{\mathrm{secondary}}[\mathrm{V}]}\)
  • \(Z_{\mathrm{pu}} = \frac{Z_{\%}}{100}\)
  • \(I_{\mathrm{fault}}[\mathrm{A}] = \frac{I_{\mathrm{rated}}[\mathrm{A}]}{Z_{\mathrm{pu}}}\)
  • \(\mathrm{SCA}[\mathrm{MVA}] = \frac{k_{\mathrm{phase}}V_{\mathrm{secondary}}[\mathrm{V}]I_{\mathrm{fault}}[\mathrm{A}]}{10^6}\)
Transformer Tap Voltage Calculator
  • \(V_{S0} = V_{S,\mathrm{rated}} \times \frac{V_{P,\mathrm{measured}}}{V_{P,\mathrm{rated}}}\)
  • \(\mathrm{Tap\ correction} = n_{\mathrm{tap}} \times \mathrm{tap\ step\ percent}\)
  • \(V_{S,\mathrm{tap}} = V_{S0} \times (1 + \frac{\mathrm{tap\ correction}}{100})\)
  • \(\mathrm{Nearest\ tap}: \mathrm{choose\ the\ listed\ step\ closest\ to\ the\ target\ voltage}\)
Transformer UPS Capacity Calculator
  • \(S_{\mathrm{UPS}}[\mathrm{kVA}] = \frac{P_{\mathrm{UPS}}[\mathrm{kW}]}{PF}\)
  • \(r_{\mathrm{factor}} = 1+\frac{r_{\%}}{100}\)
  • \(S_{\mathrm{required}}[\mathrm{kVA}] = S_{\mathrm{UPS}}[\mathrm{kVA}]\times r_{\mathrm{factor}}\)
  • \(M[\mathrm{kVA}] = S_{\mathrm{transformer}}[\mathrm{kVA}] - S_{\mathrm{required}}[\mathrm{kVA}]\)
  • \(U_{\%} = \frac{S_{\mathrm{required}}[\mathrm{kVA}]}{S_{\mathrm{transformer}}[\mathrm{kVA}]}\times100\)
Transformer Voltage Drop Calculator
  • \(f_L = \frac{L}{100}\)
  • \(\theta = \cos^{-1}(\mathrm{PF})\)
  • \(\mathrm{Reg}_{\mathrm{lag}} = f_L\left(R\%\times\mathrm{PF}+X\%\times\sin\theta\right)\)
  • \(\mathrm{Reg}_{\mathrm{lead}} = f_L\left(R\%\times\mathrm{PF}-X\%\times\sin\theta\right)\)
  • \(V_{\mathrm{drop}} = V_{\mathrm{no-load}}\times\frac{\mathrm{Reg}}{100}\)
  • \(V_{\mathrm{loaded}} = V_{\mathrm{no-load}}-V_{\mathrm{drop}}\)
Transformer Voltage Ratio Calculator
  • \(a = \frac{V_P}{V_S}\)
  • \(b = \frac{V_S}{V_P}\)
  • \(\frac{V_P}{V_S} = \frac{N_P}{N_S}\)
Voltage Sag Calculator
  • \(m = 1\ \text{for single-phase}
  • \quad m = \sqrt{3}\ \text{for balanced three-phase}\)
  • \(Z_{\mathrm{source}} = \frac{V_{\mathrm{system}}}{m I_{\mathrm{fault}}}\)
  • \(V_{\mathrm{sag}} = m I_{\mathrm{step}} Z_{\mathrm{source}}\)
  • \(\text{Sag (\%)} = 100 \times \frac{V_{\mathrm{sag}}}{V_{\mathrm{system}}}\)
  • \(V_{\mathrm{remaining}} = V_{\mathrm{system}} - V_{\mathrm{sag}}\)

Review basis

Transformer and generator workflows are screening estimates. Confirm equipment nameplates, manufacturer instructions, utility requirements, protection, grounding, and local authority requirements before final selection.

Everything under Power Quality And Transformers is a calculation from values you enter, not an approval. The pages here cite ANSI C57, IEC, and IEEE among their basis, so confirm the edition adopted in your jurisdiction against the source text before relying on a number for design or installation.

Where to go next: Motors And Starters and Motors, Starters And VFD and the formula reference, all calculators, or printable worksheets for the same calculations.